How to simulate btx separation via dividing-wall column

Benzene/toluene/ethylbenzene split into three purified products by a single rigorous dividing-wall column (prefractionator + two coupled main columns) instead of two ordinary columns in series — the thermally-coupled route real DWC retrofits use.

Also known as: BTX dividing-wall column, benzene toluene xylene separation.

FEED
feed
dist
side
btms
Qc
Qr
DWC
Light
MID
Heavy
  1. 1
    Open the ready-made model

    Open the "BTX separation via dividing-wall column" model in the MaximaLabs workspace — no install, no license. It loads live on the canvas, ready to edit and run.

  2. 2
    Confirm the thermodynamics

    This process is modeled with the PENG-ROBINSON property package over benzene, toluene, ethylbenzene — already selected, so the phase equilibrium and enthalpy are physically consistent from the first run.

  3. 3
    Review the flowsheet

    The flowsheet chains DWC. Every block is a real, solvable unit op you can reconfigure on the canvas.

  4. 4
    Run the simulation

    Click Run. The deterministic solver converges the material and energy balances (recycles included) and fills the live stream table — the AI never invents a number.

  5. 5
    Read the results and iterate

    Inspect the converged streams, tweak a spec, and re-run — or ask the AI copilot to explain a result or diagnose a failed solve in plain English.

What you'll build
Thermodynamics
PENG-ROBINSON
Components
benzene, toluene, ethylbenzene
Unit operations
DWC
Open this model in the workspace

Opens live on the canvas — free, no install.

Explore the model & flowsheet

Frequently asked questions

What does the BTX separation via dividing-wall column model simulate?
Benzene/toluene/ethylbenzene split into three purified products by a single rigorous dividing-wall column (prefractionator + two coupled main columns) instead of two ordinary columns in series — the thermally-coupled route real DWC retrofits use.
Is "BTX separation via dividing-wall column" the same as a BTX dividing-wall column?
Yes — this model covers what is also called BTX dividing-wall column, benzene toluene xylene separation. It runs the real process on the rigorous solver, so you can size and study it directly.
Which thermodynamic method does it use?
The PENG-ROBINSON property package, over benzene, toluene, ethylbenzene — already selected. You can switch the method on the canvas before running.
Which unit operations are in the flowsheet?
It chains DWC. Every block is a real, solvable unit operation you can reconfigure, add to, or remove.
Do I need to install software or buy a license?
No. BTX separation via dividing-wall column runs entirely in your browser on MaximaLabs — free, no install, no license. Open the model to load it live and run the deterministic solver.

More guides like this

Mont Belvieu NGL fractionation complex, Texas, USA

NGL fractionation: single-shell Petlyuk dividing-wall column

A natural-gas-liquids cut (ethane / propane / n-butane) split into three on-spec products by ONE thermally-coupled dividing-wall column instead of two columns in series. This uses the native Petlyuk unit op: a prefractionator whose reflux and boilup are supplied by the main column (the single condenser + single reboiler), solved by an outer Wegstein loop that converges the bidirectional vapor/liquid coupling to self-consistency — the coupling legacy sequential-modular solvers approximate with two connected columns whose recycle fails to converge.

Reference model (ChemSep)

DME synthesis via reactive distillation

Methanol dehydrates to dimethyl ether over the reactive stages of a column — reaction and separation in one shell, pulling DME overhead while unconverted methanol and water leave the bottoms (Peng-Robinson EoS avoids the missing UNIFAC group-decomposition for ethers that blocks this under an activity-coefficient package).

Aromatics complex, Ulsan, South Korea

BTX aromatics train

Benzene / toluene / p-xylene split in a two-column train — 99+% purity on all three products. From the ChemSep casebook (CScasebook_BTX).

Reference model (Dejanovic et al. 2011)

Reformate splitter via dividing-wall column

A refinery catalytic-reformer stream (benzene/toluene/o-xylene plus a non-aromatic n-heptane proxy) is split into three purified aromatics cuts by a single thermally-coupled dividing-wall column instead of two ordinary columns in series — the same DWC economics as the BTX example, applied to a genuine reformate splitter duty. Dejanovic, Matijasevic, Jansen, Olujic, "Designing a Packed Dividing Wall Column for an Aromatics Processing Plant," Ind. Eng. Chem. Res. 2011, 50, 5680.

LNG receiving and export terminal

LNG front end and storage: guard beds, tank boil-off, driver limit

The parts of a 5.2 Mtpa LNG train that are not the cold box, and the four questions they answer that no bulk unit can — at real capacity, so the vessel sizes and duties are ones an engineer can check against their own plant. Guard beds: a sulfur-carbon bed takes mercury from 200 to 0.01 µg/Nm³ — the brazed-aluminium limit, because mercury attacks the plate-fin cold box by liquid-metal embrittlement — on a 4.8 m x 6.6 m bed with 4.2 years of life from a capacity balance — inside the 3-5 year window these non-regenerable beds are actually replaced on, which is what a turnaround plan needs. A 4A molecular sieve then dries the gas to 0.1 ppmv, the only route to a cryogenic water spec (a glycol contactor tops out near a −30 °C dew point), on a 4.9 m x 5.1 m bed running a 13.8 h cycle for 1.3 MW of regeneration duty. Storage: the LNG goes to a tank whose boil-off rate comes from a 0.05%/day guarantee but whose boil-off composition comes from a real equilibrium flash — and that is the interesting part, because the vapour leaves at ~11 mol% nitrogen against 1.1% in the feed. Nitrogen and methane are far more volatile at 113 K, so the boil-off is light and the stored liquid weathers heavier: nobody specified that, the flash found it. Recondensing: the boil-off goes back into the send-out LNG rather than to a flare, and the unit reports the LNG:BOG ratio (1999) against the minimum the energy balance demands (3.8), which is the constraint a terminal is actually operated against. The driver: a gas turbine burning plant fuel gas, rated 97.5 MW at ISO conditions, delivers only 84.5 MW at 35 °C — 5.5 MW short of its 90 MW refrigeration load, and flagged as such. That derate is computed from two physical effects (a fixed-geometry compressor swallows a fixed volume so mass flow follows air density, and hotter air costs more to compress), not from a vendor curve, and it comes out at 0.66%/K — mid-band for industrial machines. It is why a tropical LNG train makes less product in summer.

Ichthys LNG, Darwin, Northern Territory, Australia

Gas-condensate LNG train: condensate, LPG and LNG

The LNG plant that is also a liquids plant, at real capacity: this is one 4.4 Mtpa train (a two-train plant is two of these), not a scaled-down sketch. A condensate-rich field arrives by trunkline as a two-phase stream: the slug catcher drops ~20 mol% of it out as raw condensate before a single molecule reaches the cold end, and the plant then runs two trains side by side off one feed. Liquids: the raw condensate is let down to an MP flash that strips the dissolved methane (without it the stabilizer's shortcut total condenser tries to condense methane at 8 bar, which is not a real stabilizer overhead), then stabilized to a C₅/C₆ product. Gas: sweetened and dried, chilled to 245 K to knock out an NGL cut, and the NGL demethanized and split by a deethanizer / depropanizer / debutanizer sequence into commercial propane (~98 mol%) and butane (~98 mol%) LPG plus a natural-gasoline bottoms. LNG: the lean gas goes to the same APCI C3MR cold end as the 'c3mr-lng-liquefaction' showcase — propane precool, mixed-refrigerant MCHE to 120 K, JT letdown to a 1.5 bar end-flash drum. Five sold products come out of one flowsheet, each a stream the solver computed. Watch the end-flash boil-off: it leaves at ~13 mol% nitrogen against 1 mol% in the feed, because the flash drum is where an LNG train actually rejects its nitrogen — nobody specified that, the flash found it. Dehydration is the real molecular-sieve bed, not a stand-in: a 4A sieve sized by length-of-unused-bed, which is what actually takes the gas to the <=0.1 ppmv the cold box needs — 95 t of sieve on a 5.5 x 5.5 m bed, a 17.5 h cycle and 1.4 MW of regeneration duty, with 0.47 bar of Ergun pressure drop. The AGRU spec is checked against the physics rather than assumed: 99.9% CO₂ removal leaves 33 ppmv, and at the coldest point in the train (115.9 K) the solid-CO₂ solubility limit is 232 ppmv on the measured-data basis — a 7x margin, so the sweetening spec demonstrably clears freeze-out instead of merely looking tight.